Dr. Babasaheb Ambedkar Convention Center till March 15 preparation instructions

 Nagpur, d. 23: Dr. Babasaheb Ambedkar Convention Center is an important project that will bring glory to the country. This project has started from 15th September 2015 and the project is getting completed. With a view to inaugurate on April 14, instructions have been given to the officers of the Nagpur Metropolitan Region Development Authority by Dr. Siddharth Gaikwad, Regional Deputy Commissioner, Social Welfare Department, to complete the work of the project by March 15. Dr. Babasaheb Ambedkar Convention Center or Prakalpacha to review the construction and also for the early completion of Sadar Prakalpa, he visited the Prakalpachi thoroughly. Assistant Commissioner Social Welfare Sukeshini Telgote was present on this occasion.
Nagpur and Rajya's lavish or planned parking and lift facilities, Lower ground floor, Ground floor - 400-seat banquet hall with kitchen and pantry, Dining hall, Business center and reception, Both conference halls with 100-seat capacity per hall, Media center The hall is the bank. First Floor or Restaurant, Foundation Office. Second floor - or Public e-library with 200 capacity and Dr. Babasaheb Ambedkar's 40 feet high bronze statue, Third floor - or Buddhist Studies Division, Research Center, Fourth floor - Auditorium with 700 capacity, Whovers Gallery Museum and Art Gallery, Wheel .ip Guest room, fifth floor auditorium balcony, V.I.P guest room, training hall and waiting room etc. have been included. Instructions have been given to do it better or Dr. Siddharth Gaikwad, the builder of the project, is giving attention.
131.68 crores has been approved for the project and Rs.113.74 crores have been spent and the additional expenditure of Rs.14.94 crores has been approved administratively as per the government's decision dated 14.11.2022. Sadar Nidhi will soon be transferred to the Nagpur Metropolitan Region Development Authority, and the 40 feet high bronze statue of Dr. Babasaheb Ambedkar will be approved soon for an additional expenditure of Rs.3.00 crore, Dr. Gaikwad said at this time. 95 percent work of Sadar Prakalpa has been completed and soon the other works will be completed, according to officials present at Nagpur Metropolitan Development Authority. Or Mr. Bhajipale, Superintending Engineer, Nagpur Improvement Trust Chimurkar, Executive Engineer, Sh. Sandeep Kamble, Architect and Balpande, Executive Engineer etc. would have been present